I just had my roof replaced. Contract was 1/3 down, 2/3 on completion. I have a punch list of items I want fixed, including some siding damage they did, before I hand over the final payment.
So far, no problem. the company will send out a representative to document the issues and put them in front of the owner.
My instinct says to not pay the balance until I have a resolution. If I hold the chips, I might get it fixed. If they hold, then I might not get anything.
My question is who decides the job is complete, and the contractor is to be paid?
Question
Turdus
I just had my roof replaced. Contract was 1/3 down, 2/3 on completion. I have a punch list of items I want fixed, including some siding damage they did, before I hand over the final payment.
So far, no problem. the company will send out a representative to document the issues and put them in front of the owner.
My instinct says to not pay the balance until I have a resolution. If I hold the chips, I might get it fixed. If they hold, then I might not get anything.
My question is who decides the job is complete, and the contractor is to be paid?
Thanks.
8 answers to this question
Recommended Posts
Archived
This topic is now archived and is closed to further replies.